The Town of Summerville contracted SILD to create a new 2.6 acre stormwater pond. Clearing the heavily wooded site was done carefully and quickly to cause minimal disturbance to nearby residents. Approximately 38,000 cubic yards of dirt was removed to form the new stormwater pond. SILD completed the majority of earthwork excavations in a 1 month span.
Long Savanna
Sea Island Land Development (SILD) was selected by Pulte Home Company to perform the complete site development for Long Savannah, a new 14.15-acre residential community located in the City of Charleston, South Carolina. The project will include the development of 69...