The St. Andrew’s PSD project was unique in that the site had been previously used as a wastewater treatment facility and a residential landfill. SILD worked closely with design engineers and the general contractor, Trident Construction, to ensure all unsuitable soils were removed from structural areas. Overall, 11,000 cubic yards of unsuitable soils were excavated and replaced structurally sound fill material.
MUSC FSER
Sea Island Land Development (SILD) was selected by MB Kahn (General Contractor) to perform the complete sitework, water and sewer utilities, and storm drainage installation for the new MUSC 24-Hour Free-Standing Emergency Room (FSER) in West Ashley, adjacent to...