The St. Andrew’s PSD project was unique in that the site had been previously used as a wastewater treatment facility and a residential landfill. SILD worked closely with design engineers and the general contractor, Trident Construction, to ensure all unsuitable soils were removed from structural areas. Overall, 11,000 cubic yards of unsuitable soils were excavated and replaced structurally sound fill material.
Dorchester District Two Middle School Site
SILD was selected as the site contractor for the new 20 acre East Edisto Middle School Campus by Thompson Turner Construction. The 135,000 square feet building pad required chemical stabilization for on time delivery. Utility construction included 2,000 linear feet...